Rail plan aims to boost capacity and permit Vande Bharat on a key Nanded corridor
Indian Railways has sanctioned a ₹163 crore project to upgrade the electric traction system on the Parbhani–Mudkhed double-line section in the Nanded Division of South Central Railway, the Railway Ministry said on Tuesday. The scheme covers conversion of the present 1×25 kV traction system to a 2×25 kV system over a stretch of 164 Track Kilometres and includes strengthening of the power supply infrastructure to meet higher electrical loads.
The Ministry described the initiative as part of Indian Railways’ continuing effort to modernise electrical infrastructure on high-density corridors. The upgraded traction and enhanced power-feeding arrangements are intended to improve operational efficiency, allow higher freight throughput and enable the running of Vande Bharat Express trains on the section.
strengthening railway infrastructure
Officials said the technical conversion from 1×25 kV to 2×25 kV aims to provide greater redundancy and capacity in traction power distribution. The revised configuration will allow heavier and faster trains to be handled with improved stability of supply, particularly during peak freight movements.
- Project cost: ₹163 crore
- Corridor: Parbhani–Mudkhed double-line, Nanded Division
- Length covered: 164 Track Kilometres
- Technical change: Conversion from 1×25 kV to 2×25 kV traction
- Expected outcomes: Higher freight capacity, support for Vande Bharat operations, improved power reliability
Local implications for freight, passenger services and power feeding
For Nanded and surrounding talukas, the upgrade is likely to have immediate operational effects on freight movement and scheduling. The Ministry linked the scheme to national freight targets, noting it will contribute to Indian Railways’ objective of achieving 3,000 Million Tonnes of freight loading by 2029-30. Enhanced traction capability on the Parbhani–Mudkhed section — a part of the Nanded Division network — is expected to ease train handling on a corridor that services agricultural and industrial consignments from the region.
Railway engineers will also augment the power supply infrastructure alongside the traction conversion to meet the increased electrical demand of heavier and faster services. The upgraded feeders and substations are intended to reduce voltage fluctuations and ensure consistent traction power, particularly important if semi-high-speed services such as Vande Bharat Express are introduced.
| Item | Detail |
|---|---|
| Sanctioned amount | ₹163 crore |
| Section | Parbhani–Mudkhed (Double line), Nanded Division |
| Track length | 164 Track Kilometres |
| Traction change | From 1×25 kV to 2×25 kV |
Railway officials emphasised that the scheme forms part of broader electrification and modernisation drives on high-density routes across the country. While the ministry statement did not specify the project timeline or contractor details, the technical nature of the work will require close coordination between signalling, traction and electrical departments to minimise service disruption during execution.
Local traders, freight operators and passengers stand to benefit if the upgrade reduces transit times and improves timetable reliability. The capacity enhancement could also attract higher freight volumes through the Nanded Division, aligning with Indian Railways’ national freight targets and regional economic objectives.
Work on the corridor will be monitored by South Central Railway authorities, who will also be responsible for sequencing interventions to ensure safety and continuity of train services while the traction and power-supply works proceed.