The Karnataka State Expert Appraisal Committee (SEAC) has granted environmental clearance for a dedicated cargo and passenger terminal at Mangaluru Old Port that will handle vessels bound for Lakshadweep, clearing a major regulatory hurdle for a project long sought by the Union Territory administration. The clearance was issued during the SEAC meeting in Bengaluru on May 30, paving the way for construction to commence in August after outstanding agreement formalities are completed.
Project background and approvals
The proposal for a dedicated maritime link from Mangaluru to Lakshadweep was first advanced by the Lakshadweep Administration in 2011. Subsequent institutional steps included an agreement with the Karnataka Ports Department and technical approval from the Karnataka Maritime Board to construct a specialised jetty. The scheme was announced in the Karnataka State Budget for 2022–23 and placed under the Centre’s Sagarmala programme.
Union funding for the terminal was approved by the Ministry of Ports, Shipping and Waterways on 20 July 2022. The construction contract was awarded to Bengaluru-based Ramalingam Construction Company Pvt Ltd on 29 March 2023.
Scope, cost and facilities
The terminal, to be developed on land belonging to the Ports and Inland Water Transport Department on the northern side of Mangaluru Old Port, carries an estimated cost of ₹65 crore. It will provide separate berths for cargo and passenger operations. Around 9,800 sq ft has been earmarked for cargo handling while approximately 6,000 sq ft will be used for passenger services. Planned amenities include a cruise lounge alongside other passenger facilities.
| Item | Detail |
|---|---|
| Project cost | ₹65 crore |
| SEAC clearance | 30 May |
| Contractor | Ramalingam Construction Company Pvt Ltd (contract awarded 29 March 2023) |
| Allocated cargo area | 9,800 sq ft |
| Allocated passenger area | 6,000 sq ft |
Delays and implementation timeline
Although the contract envisaged completion within 30 months of work start, excluding monsoon interruptions, the project encountered prolonged delays before SEAC clearance. Officials attribute the hold-up to multiple statutory clearances that were required, including Coastal Regulation Zone approvals and mandatory public consultations. Nearly three years were spent securing the permissions that had stalled construction.
Prior to beginning physical works, existing installations at the port site — including a fuel station and a ferry service terminal that serves Bengre — will be relocated to make way for the new infrastructure.
Local impact and operational aims
The terminal is expected to strengthen maritime connectivity between Karnataka and Lakshadweep by offering modernised facilities for both cargo and passenger movements. Officials have presented the scheme as a measure to improve logistics efficiency for supplies to the islands and to create a better arrival and departure experience for travellers using passenger vessels and cruise services.
Once operational, the dedicated berth for Lakshadweep-bound vessels could reduce turnaround time for cargo handling and provide a focused passenger processing area that includes a cruise lounge, potentially facilitating tourism-linked calls as well as regular ferry operations.
- Environmental clearance from SEAC obtained on 30 May.
- Construction expected to start in August after completion of agreement formalities.
- Contractor appointed in March 2023; project cost estimated at ₹65 crore.
Stakeholders will monitor the completion of outstanding formal agreements and the relocation of existing port facilities ahead of the announced August start. The project’s progress is likely to be watched closely by administrators in Lakshadweep, shipping operators and traders who rely on the Mangaluru–Lakshadweep maritime corridor.