Kanpur: The National Highways Authority of India (NHAI) has suspended toll collection on the newly inaugurated 63‑km Kanpur–Lucknow Expressway until identified defects are fully rectified, after multiple stretches of the road showed signs of slippage and surface failure within days of opening, officials said.
Immediate action, contractor penalised
The expressway, officially designated National Expressway‑6 (NE‑6), was opened on 13 July. NHAI said it has initiated action against the concessionaire and contractor PNC Infratech Ltd, declaring the firm a non‑performer. If confirmed, this status will make the company ineligible to bid for future NHAI projects.
Alongside the non‑performance notice, NHAI issued a show‑cause notice proposing a penalty equivalent to 2% of the performance security and moving to initiate debarment proceedings for up to three years against the head of highways and other responsible staff.
- Length: 63 km
- Project cost: ₹4,200 crore
- Lanes: Six
- Opening: 13 July
- Reported slippage: 26 July (near 64‑km mark, Korari area, Unnao)
Investigation and technical probe
To probe the failures, NHAI has constituted an expert committee from IIT Kharagpur, the authority said. A senior NHAI official estimated the rectification cost at around ₹3 crore and added that the contractor would be required to bear the expense, with no financial implication for NHAI. The official also said the loss of toll revenue would be recovered from the contractor.
Traffic has been diverted at the affected stretch, reported near a bridge approach in Unnao's Korari area, where a slippage spanning roughly 300 metres was observed, according to the authority. The damage was widely shared on social media and raised questions about construction quality.
Personnel actions and debarment notices
In addition to action against PNC Infratech, NHAI removed and debarred several project personnel. The project manager of the construction agency, the team leader of the independent engineer and the resident engineer have been removed from the project and debarred from participating in any highway projects for two years, the authority said.
Theme Engineering Services Pvt Ltd, which served as the independent engineer on the project, has also received a debarment notice, NHAI added.
| Item | Detail |
|---|---|
| Project cost | ₹4,200 crore |
| Expressway length | 63 km |
| Opening date | 13 July |
| Reported damage | 26 July — slippage near 64‑km mark (Korari, Unnao) |
| Estimated rectification cost | ₹3 crore (contractor to bear) |
The expressway was inaugurated amid high expectations that it would cut travel time between Uttar Pradesh's capital and its industrial hub — reducing the journey from about 90 minutes to roughly 40 minutes. Union ministers and state leadership had attended the opening ceremony.
Authorities said the surface failures surfaced after heavy rainfall and included cave‑ins and subsidence at multiple stretches. The latest reported defect was close to a bridge approach in Unnao, where portions of the embankment showed renewed subsidence despite earlier repair work, forcing further traffic diversions.
With toll collection suspended, NHAI has emphasised that remedial work must be completed before normal operations resume and that financial losses will be recovered from the contractor as per contract provisions.
Local commuters and logistics operators face potential disruption while traffic is diverted around the affected stretch. NHAI's technical committee from IIT Kharagpur is expected to examine construction practices, material quality and design parameters to determine causes and recommend corrective measures.
Further administrative and contractual actions, including the proposed debarments and penalties, reflect the authority's invocation of standard safeguards after early life defects on a major greenfield corridor connecting Kanpur and Lucknow.