State and Centre agree on deadline to speed up Mamnoor and Adilabad airport projects
Telangana Chief Minister A Revanth Reddy held a meeting with Union Civil Aviation Minister Kinjarapu Rammohan Naidu in New Delhi on Tuesday to discuss the planning, design and facilities for two new airports — at Mamnoor (Warangal) and Adilabad. Following the discussion, the Chief Minister said efforts are on to complete both projects by June 2, 2028.
In a statement and posts on X after the meeting, the Chief Minister said the talks covered detailed aspects of development and measures required for expeditious completion. He underlined the need for coordinated action between the central and state governments to fast-track construction.
“We are making efforts today with the target of completing the Warangal Airport, as well as the Adilabad Airport, by June 2, 2028,” the Chief Minister said.
Union Minister Naidu described the meeting as productive and indicated that the proposed Warangal airport would be developed with a scope beyond merely handling passenger travel. Details of the additional roles or facilities were not specified in the Chief Minister’s accounts released after the meeting.
Local implications for Warangal
The CM emphasised that the state government’s objective is to enhance regional air connectivity, improve transport options for residents and attract investment, industry and employment to Telangana. For Warangal, the operationalisation of Mamnoor airport is expected to:
- Improve direct air connectivity for passengers and businesses in Warangal and surrounding districts.
- Potentially attract industry and investment by shortening travel times to other metro centres.
- Create construction and airport-related employment during both the building phase and operational phase.
While the CM and the Union Minister spoke of expediting the projects, no new financial allocations, tender schedules, or timeline milestones beyond the stated completion date were released in the immediate statements. The meeting focused on design, necessary facilities and coordination measures rather than on firm funding details.
What was agreed and what remains to be decided
The published accounts from the meeting confirm agreement on collaboration and an ambitious deadline. However, several operational and procedural steps remain to be finalised before work can be completed by the target date:
- Finalisation of detailed project reports (DPRs) and design approvals for both Mamnoor and Adilabad sites.
- Clearance of required environmental and regulatory permissions, if any are pending.
- Determination of funding responsibilities between centre and state, and timelines for tenders and contractor appointments.
| Project | Location | Target completion |
|---|---|---|
| Warangal (Mamnoor) Airport | Mamnoor, Warangal | June 2, 2028 |
| Adilabad Airport | Adilabad | June 2, 2028 |
The CM’s statement reiterated the state government’s commitment to strengthening regional connectivity and to mobilising both administrative and political support for the projects. He urged that necessary actions be taken in coordination between the central and state governments to ensure rapid construction.
Local stakeholders in Warangal will be watching for the release of detailed timelines, tender notices and the DPRs that will set out the scope, passenger-handling capacity and cargo facilities. The Union Minister’s comment that Warangal’s airport could be developed beyond passenger travel hints at broader planning, but specifics were not provided in the public briefing.
For now, the June 2, 2028 deadline is the official public target. Meeting it will require timely clearances, defined funding flows and swift execution of construction contracts — steps that remain to be publicly documented in the coming weeks and months.
Reporting from Warangal.